AnsweredAssumed Answered

EXTREMELY Long DUJ Times (SPE SLM8)

Question asked by aurora.sullivan on Jul 10, 2019
Latest reply on Jul 19, 2019 by daryn.hughes

Hello,

 

Does anyone else running an SPE environment experience a really long DUJ time?

One day it will be 4 hours (which is still too long) and another day it will be 7.5 hours. I have taken into consideration that we do have certain longer application jobs that run weekly which is fine but during mid-week when nothing additional or special is taking place in the DUJ, it is taking 7-8 hours. 

 

One observation I've made is that a Job called "JobInventoryComputerSoftwareUpdate" has a time length recorded of 3hrs8mins however, when you actually add up all of the steps within the job, it's only taken 20mins48secs? I can't go through each job and check if the steps actually equate to the time stamp given of that specific job but that's a massive difference and I believe it's what is causing the DUJ to take so long. 

 

We are running SLM 8.3.09. 

 

Any advise is very much appreciated .

 

Kind regards,

Aurora.